Roots Hamburg

Germany’s tallest wooden high-rise

The Roots project is an 18-storey wooden high-rise currently under construction in Hamburg’s HafenCity. A total of 181 flats will be built here, along with exhibition rooms and the administrative offices of the Deutsche Wildtier Stiftung (German Wildlife Foundation). All upper floors will be built using solid wood floor slabs and load-bearing walls in solid wood construction, only the basement and ground floor as well as the circulation cores of the building are planned in reinforced concrete construction. This building method contributes to the reduction of the CO2 footprint, but also limits noise emissions during implementation and ensures a healthy indoor climate.

A second façade made of glass ensures fire, UV and moisture protection.

Sliding glass elements protect the all-round loggias from wind and weather. With an exhibition centre focusing on nature conservation and wildlife, Hamburg is gaining a significant venue that enthuses people about nature and biodiversity and raises their awareness of nature conservation.

Wood as a building material

65 metres in Hamburg’s HafenCity

5,500 m³ of construction timber used

4,600 t of bound CO2

1.25 kg of CO2 per m² of GFA = 5.5 times more than in a conventionally constructed reference building

No use of composite materials, which allows the complete dismantling of the building. Reuse of individual components is therefore conceivable.

Das Baumaterial ist PEFC zertifiziert und stammt aus der Steiermark in Österreich,
wo sich auch der Sägewerk von RUBNER Holzbau befindet.

The architects

Störmer Murphy and Partners

Martin Murphy

“I firmly believe that we as architects have long realized that sustainability is part of our daily agenda. For too long, architects have only talked about this, but implemented little. Like a number of other timber construction projects by Störmer Murphy and Partners, Roots is a groundbreaking example that reflects this assumed responsibility for lived sustainability.”

Kasimir Altzweig

“Making full use of design leeway and assuming responsibility. Sustainable architecture can only succeed through the responsible commitment of all those involved: clients, planners, bodies responsible for approvals and the construction industry. The Roots project has created a new normal in our office.”

3D model from the study phase

2017

Investment application procedure

2018

Start of planning phase (HOAI service phase 2)

2019

Facade mock-ups, search for timber construction company, redesign, cost optimisation

2020

Building permit, commencement of construction

2022

Assembly of timber construction

2024

Completion

Special high-rise construction

Supporting structure

„Es war stets unsere Prämisse, mit dem Rohstoff Holz verantwortungsvoll umzugehen, daher sind die Holzstützen in den Wandelementen auf das statisch notwendige Mindestmaß reduziert. Auch wollten wir Verbundkonstruktionen aus Holz und Beton vermeiden, die sich nicht sortenrein voneinander trennen lassen. Deshalb haben wir uns für massive Brettsperrholzdecken
entschieden, die untereinander verschraubt sind und später demontiert werden können."

Uta Meins, Projektleiterin Störmer Murphy and Partners

Façade

Larchwood façade

The supporting structure in solid wood construction is recyclable, thus retaining the bound CO2.

Prefabrication of complete, load-bearing façade elements (14m) lifted into position from the truck by a crane.

The more complex detail planning, which already starts in the pre-planning phase (HOAI service phase 2), is offset by an accelerated construction process due to the high level of prefabrication. Façade segments of up to 14 m in length are prefabricated in the factory and transported to the construction site on low-loaders. The assembly of one high-rise storey takes approx. 3 weeks.

Materials

“While untreated larch cladding is installed horizontally behind a protective glass skin in the high-rise building, pre-greyed vertical larch cladding is used in the elongated building. In contrast to the upper storeys, the ground floor façade is constructed as a post-and-beam structure with fibre cement panels. The brick façade on the mound level was already specified by the HafenCity design guidelines.”

Philipp Macke, project leader

Façade mock-up

“In 2019, a two-storey mock-up of the façade was built, each with two rooms behind it, in order to test various planning parameters on it. First and foremost, the aim was to determine which external and internal sound insulation measures could meet the specifications. The evaluation of the sound measurements resulted in a significant simplification of installations and parts of the construction. This applies above all to the internal sound insulation.”

Philipp Macke, project leader

Fire protection

“A high-rise building with a combustible load-bearing structure is not permitted under building regulations, so that special assessments and increased planning and coordination requirements are necessary. As part of this, ABH 23 and the Hamburg fire brigade agreed – in addition to the fire-resistant requirement (F 90) – on an additional robustness of 30 minutes (R 120. The total of 120 minutes is to be achieved both by the structural proof for combustion according to Eurocode and by fire protection cladding.”

HAHN Consult

Baustelle

"Das Holzhochhaus geht in den Bau – schnell, sauber und auf den Millimeter präzise vorgefertigte Holzbauelemente werden von dem 80 m hohen Kran in ihre Position gesetzt. Die bis zu 8 Tonnen schweren Elemente beinhalten bereits die komplett fertige Außenwand incl. vormontierer Fenster, Verkleidung der Fassade, der zurückspringenden Loggiadecke aus europäischem Lärchenholz bis hin zur Verkabelung. Insgesamt werden ca. 1200 Holzbauelemente in verschiedenen Größen verbaut, welche vornehmlich aus Fichte mit geringen Anteilen von Tanne und Kiefer sowie aus Baubuche für die hoch belasteten Stützen in den unteren Geschossen gefertigt werden."

Uta Meins, Projektleiterin Störmer Murphy and Partners

Project data

Category

Office, housing, exhibition

Size GFA


31.000 sq m

Services


HOAI service phases 1-5

Start of the planning phase


2018

Completion


2024

Clients

Garbe Immobilien-Projekte GmbH and Deutsche Wildtier Stiftung

Roots – media coverage